/Photo%201%20(1-7-03)%20-%20DSC00016.JPG)
January 7, 2003 − Excavation site preparation for the TMC foundation.
|
/Photo%202%20(1-14-03)%20-%20DSC00000.JPG)
January 14, 2003 − Removal of unsuitable soil (demucking) and site preparation for the building foundation. |
/Photo%203%20(2-5-03)%20-%20DSC00027.JPG)
February 5, 2003 − Demolition of rear section of old BCTED building to make room for new TMC construction. |
/Photo%204%20(2-13-03)%20-%20DSC00034.JPG)
February 13, 2003 − Initial placement of concrete for building foundation. |
/Photo%205%20(3-6-03)%20-%20DSC00006.JPG)
March 6, 2003 − Installation of foundation and masonry blocks. |
/Photo%206%20(3-6-03)%20-%20DSC00009.JPG)
March 6, 2003 − Installation of conduits for the emergency generator. |
/Photo%207%20(3-6-03)%20-%20DSC00008.JPG)
March 6, 2003 − Site drainage construction view of “French Drain” installation. |
/Photo%208%20(3-28-03)%20-%20DSC00014.JPG)
March 28, 2003 − Concrete placement for rear canopy foundation. |
/Photo%209%20(3-31-03)%20-%20DSC00020.JPG)
March 31, 2003 − Center view of Control Room up to finished floor level. |
/Photo%2010%20(4-1-03)%20-%20DSC00026.JPG)
April 1, 2003 − Control Room view up to finished floor level. Construction of first floor walls and concrete slab (floor). |
May 8, 2003 − Placement of concrete for the Control Room “sub-floor.” |
/Photo%2012%20(5-8-03)%20-%20DSC00026b.JPG)
May 8, 2003 − “Floating” concrete of Control Room to “smooth finish.” |
/Photo%2013%20(5-22-03)%20-%20DSC00043.JPG)
May 22, 2003 − Completed masonry walls and control room slab. Also, working on floor for area around the control room. |
/Photo%2014%20(5-22-03)%20-%20DSC00055.JPG)
May 22, 2003 − Completing remaining 1st floor concrete slab. |
/Photo%2015%20(6-26-03)%20-%20DSC00031.JPG)
June 26, 2003 − Placement of concrete over precast joist and floor slab. |
/Photo%2016%20(7-8-03)%20-%20DSC00006.JPG)
July 8, 2003 − Construction of 2nd floor structure and exterior walls. |
/Photo%2018%20(8-26-03)%20-%20DSC00004.JPG)
August 26, 2003 − Rear / South view of TMC exterior wall up to 2nd floor roof level. |
/Photo%2019%20(8-29-03)%20-%20DSC00023.JPG)
August 29, 2003 – Installation of 2nd floor roof precast joists (beams). |
/Photo%2020%20(9-2-03)%20-%20DSC00033.JPG)
September 2, 2003 – Side / East view of TMC exterior wall up to roof level. |
/Photo%2021%20(9-2-03)%20-%20DSC00034.JPG)
September 2, 2003 – Front / North view of TMC exterior wall up to roof level. |
/Photo%2022%20(9-2-03)%20-%20DSC00035.JPG)
September 2, 2003 – Broward County TMC sign structure cutout. |
/Photo%2023%20(9-3-03)%20-%20DSC00037.JPG)
September 3, 2003 − Start of exterior veneer block and waterproofing agent. |
|
|
/Photo%2025%20(9-12-03)%20-%20DSC00033.JPG)
September 12, 2003 − Completed 2nd floor topping. |
/Photo%2026%20(10-8-03)%20-%20DSC00015.JPG)
October 8, 2003 − Plate compactor preparing ground for main entrance ramp. |
/Photo%2027%20(10-8-03)%20-%20DSC00014.JPG)
October 8, 2003 − Delivery of additional interior wall stud loads. |
/Photo%2028%20(10-9-03)%20-%20DSC00024.JPG)
October 9, 2003 − Topping Off Celebration inside TMC control room. |
/Photo%2029%20(10-29-03)%20-%20DSC00011.JPG)
October 29, 2003 − Construction of the electrical generator enclosure − South end of the TMC. |
/Photo%2030%20(10-30-03)%20-%20DSC00030.JPG)
October 30, 2003 − Construction of TMC curb wall over 2nd floor. |
/Photo%2031%20(10-31-03)%20-%20DSC00035.JPG)
October 30, 2003 − Construction of TMC curb wall over 2nd floor. |
/Photo%2032%20(11-20-03)%20-%20DSC00004.JPG)
November 20, 2003 − Installation of interior drywall. |
/Photo%2033%20(11-21-03)%20-%20DSC00015.JPG)
November 21, 2003 − Installation of exterior brick wall. |
November 22, 2003 − Installation of modified bituminous membrane roofing. |
/Photo%2035%20(12-12-03)%20-%20DSC00038.JPG)
December 12, 2003 − Installation of Kohler Power Systems electrical generator (transfer switch). |
/Photo%2037%20(1-12-04)%20-%20DSC00039.JPG)
January 12, 2004 − Painting ceiling and walls of TMC Control Room. |
/Photo%2038%20(1-14-04)%20-%20DSC00047.JPG)
January 14, 2004 − Installation of front walkway canopy framing. |
/Photo%2039%20(2-5-04)%20-%20DSC00006.JPG)
February 5, 2004 − BCTED relocating signalization wires to new building. |
/Photo%2040%20(2-5-04)%20-%20DSC00013.JPG)
February 5, 2004 − Waterline tapping sleeve and valve for service to new building. |
February 5, 2004 − Chiller plants, view of piping, motors and motorized valves. |
/Photo%2042%20(2-9-04)%20-%20DSC00051.JPG)
February 9, 2004 − Aerial view of the chiller plants. |
/Photo%2043%20(2-7-04)%20-%20DSC00036.JPG)
February 7, 2004 − Early view of the Control Room and video wall cutout. |
/Photo%2044%20(2-9-04)%20-%20DSC00054.JPG)
February 9, 2004 − Aerial view of elevator shaft. |
/Photo%2046%20(3-29-04)%20-%20DSC00010.JPG)
March 29, 2004 − Installation of TMC workstation consoles and video wall frames. |
/Photo%2045%20(3-29-04)%20-%20DSC00002.JPG)
March 29, 2004 − Ladder type cable tray inside of the cross-connect room. |
/Photo%2047%20(3-30-04)%20-%20DSC00023.JPG)
March 30, 2004 − Antenna support posts on 2nd floor roof mounted on the elevator tower. |
/Photo%2049%20(4-8-04)%20-%20DSC00003.JPG)
April 8, 2004 − View of TMC Control Room at 80% completion. |
/Photo%2050%20(4-14-04)%20-%20DSC00052.JPG)
April 14, 2004 − Video wall testing. |
/Photo%2051%20(4-28-04)%20-%20DSC00030.JPG)
April 28, 2004 − Installation of office cubicles on Westside of 2nd floor. |
/Photo%2052%20(4-28-04)%20-%20DSC00021.JPG)
April 28, 2004 − Plywood sheathing for the metal wall façade to the TMC. |
/Photo%2053%20(5-24-04)%20-%20DSC00048.JPG)
May 24, 2004 − Riser conduits from the 1st floor cross-connect closet to the 2nd floor. |
/Photo%2054%20(5-26-04)%20-%20DSC00051.JPG)
May 26, 2004 − Installation of metal wall panels. |
|
|
/Photo%2055%20(6-15-04)%20-%20DSC00062.JPG)
June 15, 2004 − Construction of interior stairs leading to 2nd floor. |
/Photo%2056%20(6-17-04)%20-%20DSC00040.JPG)
June 17, 2004 − Data / Voice cabling terminated above cubicle area on 2nd floor. |
June 17, 2004 − Data patch panels. |
/Photo%2058%20(6-23-04)%20-%20DSC00015.JPG)
June 23, 2004 − Installation of stainless steel rails for the main entrance ADA ramp. |
/Photo%2059%20(6-23-04)%20-%20DSC00040.JPG)
June 23, 2004 − Construction of the side / east parking lot including placement of asphaltic concrete over primed lime rock base. |
/Photo%2060%20(6-23-04)%20-%20DSC00049.JPG)
June 23, 2004 − Placement of asphalt by hand under rear covered parking area. |
/Photo%2061%20(7-8-04)%20-%20DSC00024.JPG)
July 8, 2004 − Delivery of tropical trees and plants for landscaping. |
/Photo%2062%20(7-12-04)%20-%20DSC00008.JPG)
July 12, 2004 – View of side / east parking lot. |
/Photo%2063%20%20(7-28-04)%20-%20DSC00013.JPG)
July 28, 2004 − View of completed electrical generator enclosure. |
/Photo%2064%20(8-13-04)%20-%20DSC00001.JPG)
August 13, 2004 – Front / North view of completed TMC. |
/Photo%2065%20(9-17-04)%20-%20DSC00026.JPG)
September 17, 2004 – Equipment Cabinet / Data Servers. |
/Photo%2066%20(9-20-04)%20-%20DSC00033.JPG)
September 20, 2004 − View of completed TMC Control Room. |
/Photo%2067%20(10-4-04)%20-%20DSC00031.JPG)
October 4, 2004 – Side / East view of completed TMC. |
/Photo%2068%20(10-14-04)%20-%20DSC00010.JPG)
October 14, 2004 − View of the Broward County TMC sign. |
/Photo%2069%20(12-29-04)%20-%20OutsideBuliding.jpg)
December 29, 2004 − Northeast view of completed TMC.
|
|