| Key
Events
October 31,
2002 – Beginning of
TMC Construction Contract
December 1, 2002 – Groundbreaking
of TMC Site
January 7, 2003 – Removal
of Unsuitable Soils (Demucking)
February 13 to March 28, 2003 – Placement
of Concrete for Building Foundation
February 20, 2003 – First
Section of Concrete Poured for Building Foundation
March 3, 2003 to June 26, 2003 – 1st
Floor Construction (Structure Only)
March 6, 2003 – Electrical
Conduit Installation from Outside Generator to
Electrical Room
June 19, 2003 to June 26, 2003 – 1st
Floor Topping
June 26, 2003 to September 12, 2003 – 2nd
Floor Construction (Structure Only)
July 22, 2003 to November 30, 2003 – Interior
Framing (Both Floors)
September 12, 2003 – 2nd
Floor Topping (Concrete for Roof)
October 8, 2003 to December 2, 2003 – Waterproofing
of Exterior Walls
October 9, 2003 – Topping
Off Celebration
October 18, 2003 – Video
Wall Framing
October 29, 2003 to January 12, 2004 – Exterior
Veneer Block
November 22, 2003 to December 2, 2003 –
Roofing
December 10, 2003 to April 30, 2004 – Data
/ Voice Cabling
February 2, 2004 to May 6, 2004 – Exterior
Metal Wall Substructure
February 7, 2004 – Control
Room Shell Completed
February 18, 2004 – Workstation
Console Installation
March 9, 2004 to April 9, 2004 – ITS
/ Computer Systems Installation
March 22, 2004 to April 14, 2004 – Video
Wall Display Installation
April 15, 2004 to May 30, 2004 – ITS
/ Computer Systems Testing
April 21, 2004 to June 10, 2004 – Cubicle
/ Modular Furniture
April 23, 2004 to July 7, 2004 – Side
/ East Parking Lot and Curbing
July 23, 2004 – Exterior
Building Completed
September 6, 2004 to September 20, 2004 –
Office Furniture Deliver
and Installation
September 1, 2004 – Temporary
Certificate of Occupancy (TCO)
September 20, 2004 – Official
Opening Day of TMC
|